Open Product/Process CR PC021517-1 Detail |
Title: Eliminate CenturyLink Search PCAT | ||||||
CR Number |
Current Status Date |
Area Impacted | Products Impacted | |||
|
||||||
PC021517-1 |
Completed 5/17/2017 |
CenturyLink Search (aka QSearch) |
Originator: Gomez, Lee |
Originator Company Name: CenturyLink |
Owner: Gomez, Lee |
Director: |
CR PM: Lorence, Susan |
Description Of Change |
CenturyLink Search (AKA) QSearch is an Electronic Directory Assistance (EDA) Service. Since the first availability of this product prior to 2004, there have been no inquiries or show of interest.
CenturyLink would like to eliminate this product effective 4/30/2017.
|
Date | Action | Description |
2/17/2017 | CR Acknowledged | CR Acknowledged. |
2/15/2017 | CR Submitted | CR Submitted. |
3/15/2017 | Status Changed | Status changed to Presented. |
3/16/2017 | Communicator Issued | See notification number PROD.MISC.03.16.17.F.15404.Elim_CenturyLink_Search. |
3/16/2017 | Status Changed | Status changed to Development. |
3/15/2017 | Discussed at Monthly CMP Meeting | Discussed in the March Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
4/14/2017 | Communicator Issued | See notification number PROD.MISC.04.14.17.F.15477.Fnl_Elim_CenturyLink_Srch. |
4/19/2017 | Discussed at Monthly CMP Meeting | Discussed in the April Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
4/30/2017 | Status Changed | Status changed to CLEC Test. |
5/17/2017 | Status Changed | Status changed to Completed. |
5/17/2017 | Discussed at Monthly CMP Meeting | Discussed at the May Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
Project Meetings |
5/17/17 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that the final notification was sent April 14, 2017 with an effective date of April 30, 2017. There were no customer comments. This CR has been in CLEC Test since the April 30 date. CenturyLink would like to move this to a Completed status. There were no objections. 4/19/17 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented last month by Lee Gomez. CenturyLink sent a Level 4 notice to eliminate the PCAT. The final notification PROD.MISC.04.14.17.F.15477.FnlElimCenturyLinkSrch was sent April 14, 2017 with effective date of April 30, 2017. No customer comments were received. This CR will be moved to CLEC Test as of that date. 3/15/17 Product/Process CMP Meeting Lee Gomez – CenturyLink presented this new CR to eliminate the CenturyLink Search which was previously known as QSearch. Lee said there has been no show of interest in this product and we would like to eliminate as of the end of April. Lee asked if there were any questions. Susan Williams – CenturyLink asked how this product was offered. John Hansen – CenturyLink confirmed this product was not in the ICA and said there was agreement to send this notification as a level 4 with an April 30, 2017 planned effective date. There were no other questions.
|
Information Current as of 1/11/2021