Open Product/Process CR PC020216-1 Detail |
Title: Eliminate Directory Listing Migration Daily Report | ||||||
CR Number |
Current Status Date |
Area Impacted | Products Impacted | |||
|
||||||
PC020216-1 |
Completed 5/18/2016 |
Directory Listings |
Originator: Gomez, Lee |
Originator Company Name: CenturyLink |
Owner: Gomez, Lee |
Director: |
CR PM: Lorence, Susan |
Description Of Change |
CenturyLink currently offers CLECs the option to request a Directory Listing Migration Daily Report to use to verify the completion of Conversion/Migration orders to FBDL.
This report has not been requested by any customer in at least 10+ years. CenturyLink is planning to eliminate this process and reporting capability.
|
Date | Action | Description |
2/4/2016 | CR Acknowledged | CR Acknowledged. |
2/2/2016 | CR Submitted | CR Submitted. |
2/17/2016 | Status Changed | Status changed to Presented. |
2/17/2016 | Discussed at Monthly CMP Meeting | Discussed in the February ProdProc CMP Meeting - See Attachment D in the Distribution Package. |
3/1/2016 | Status Changed | Status changed to Development. |
3/16/2016 | Discussed at Monthly CMP Meeting | Discussed in the March ProdProc CMP Meeting - See Attachment D in the Distribution Package. |
3/21/2016 | Communicator Issued | See notification number PROS.LIST.03.21.16.F.14388.DLPBP_V69. |
4/20/2016 | Discussed at Monthly CMP Meeting | Discussed in the April ProdProc CMP Meeting - See Attachment D in the Distribution Package. |
4/20/2016 | Communicator Issued | See notification number PROS.LIST.04.20.16.F.14473.Final_DLPBP_V69. |
5/5/2016 | Status Changed | Status changed to CLEC Test. |
5/18/2016 | Status Changed | Status changed to Completed. |
5/18/2016 | Discussed at Monthly CMP Meeting | Discussed in the May ProdProc CMP Meeting - See Attachment D in the Distribution Package. |
Project Meetings |
5/18/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR is associated with the elimination of this daily Directory Listings Migration report that customers have not requested in over 10 years. No comments were received on the level 4 notification to update the Directory Listing Providers Business Procedure. Mark said this CR has been in CLEC Test since May 5, 2016 and we would like to move it to a Completed status. There were no objections. 4/20/16 Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented in the February meeting by Lee Gomez. The Level 4 notification to update the Directory Listing Providers Business Procedure was distributed March 21, 2016 via a Process notification. The comment cycle ended on April 5, 2016 and no comments were received. Mark said the final notice is due to be distributed April 20, 2016 with a proposed effective date is May 5, 2016. There were no comments. 3/16/16 Product/Process CMP Meeting Mark Coyne – CenturyLink said this CR was presented in the February meeting and that a level 4 notification to update the Directory Listing Providers Business Procedure had gone out March 15, 2016 with a proposed effective date of April 29, 2016. CenturyLink NOTE: The level 4 notification to update the business procedure was distributed on March 21, 2016 and has a proposed effective date May 5, 2016. 02/17/16 Product/Process CMP Meeting Lee Gomez – CenturyLink presented this new CR. Lee said is does not appear any customer has ever requested this report and we would like to eliminate it. Lee asked if there were any questions. There were none.
|