Open Product/Process CR PC012908-1 Detail |
Title: Elimination of Virtual to Cageless Collocation conversion option | ||||||
CR Number |
Current Status Date |
Area Impacted | Products Impacted | |||
|
||||||
PC012908-1 |
Completed 5/21/2008 |
Originator: Buckmaster, Cindy |
Originator Company Name: Qwest Corporation |
Owner: Buckmaster, Cindy |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Elimination of Virtual to Cageless Collocation conversion option
|
Date | Action | Description |
1/29/2008 | CR Submitted | CR Submitted |
1/29/2008 | CR Acknowledged | CR Acknowledged |
2/22/2008 | Status Changed | Status changed to Presented |
2/22/2008 | Discussed at Monthly CMP Meeting | Discussed at the February CMP Meeting - See Attachment D in the Distribution Package |
3/4/2008 | Status Changed | Status changed to Development |
3/4/2008 | Communicator Issued | PROS.03.04.08.F.05243.Elim_ColloVirtualPhysOvrv |
3/19/2008 | Discussed at Monthly CMP Meeting | Discussed at the March Prod/Proc CMP Meeting - See Attachment D in the Distribution Package |
4/3/2008 | Communicator Issued | PROD.04.03.08.F.05305.FNL_Elim_ColloVirtualPhys |
4/16/2008 | Status Changed | Status changed to CLEC Test |
4/16/2008 | Action Item Created | Discussed at the April CMP Meeting - See Attachment D in the Distribution Package |
5/21/2008 | Status Changed | Status changed to Completed |
5/21/2008 | Discussed at Monthly CMP Meeting | Discussed at the May Monthly CMP Meeting - See Attachment D in the Prod/Proc CMP Meeting |
Project Meetings |
5/21/08 Product/Process CMP Meeting Mark Coyne-Qwest stated that this request has an effective date of 4/18/08 and that we would like to close this CR. Kim Isaacs-Integra said that this request was implemented over their objection. Bonnie Johnson-Integra agreed that this request was implemented over their objection (5/27/08 Comment to minutes received from Integra) and Qwest would close it over our objection. Mark Coyne-Qwest said that Integra’s objection has been noted. April 16, 2008 Product/Process CMP Meeting Mark Coyne-Qwest stated that this request has an effective date of 4/18/08 and will be revisited in May. March 19, 2008 Product/Process CMP Meeting Mark Coyne-Qwest stated that the notice went out on 3/4/08 with an effective date of 4/18/08 and the comment cycle closes today. Susan Lorence-Qwest stated that the comment cycle did close today and there were no comments. February 20, 2008 Product/Process CMP Meeting Lynn Stecklein-Qwest presented this CR on behalf of Cindy Buckmaster (Qwest). This request is for the elimination of the Virtual to Cageless Collocation conversion option. She said that changes from one form of collocation to another require complete construction of the new collocation and decommissioning of the old collocation. Bonnie Johnson-Eschelon asked why Qwest was doing this. Lynn Stecklein-Qwest stated that the volumes were very low for the conversion option and that there have only been approximately 5 in 10 years. Bonnie Johnson-Eschelon said that they would take this back and may have more questions.
|