Title: Tech Pub 77386 Shorten Level 3 Notification interval to coincide with Tariff implementation date of February 20, 2007
CR Number Current Status
Date
Area Impacted Products Impacted

PC012307-1EX Completed
2/7/2007
Collocation, Resale
Originator: Farra, Jeff
Originator Company Name: Qwest Corporation
Owner: Farra, Jeff
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest is requesting that the Level 3 changes to Technical Publication 77386 Issue L associated with notification NETW.01.22.07.F.04464.Tech_Pub_77386_IssL be implemented in a shorter interval than normal. The proposed documentation changes to Tech Pub 77386 include language associated with adding new features to the MOE product related to Collocation. The change is to add Ethernet connectivity options to the optical ITP.

The CR is being submitted as an exception request to implement a Level 3 notification in a shorter than normal timeframe. The minimum required interval is 31 days. Qwest is requesting the proposed change be implemented in a 29 day interval to match the tariff implementation date of February 20, 2007.


Date Action Description
1/23/2007 CR Submitted  
1/23/2007 CR Acknowledged  
1/29/2007 Communicator Issued CMPR.01.29.07.F.04483.ExceptionVoteRequired 
2/6/2007 Communicator Issued CMPR.02.07.07.F.04502.CMP_Vote_Disposition 
2/6/2007 Status Changed Status changed to Completed 

Project Meetings

Vote Required

PC012307-1EX Tech Pub 77386 Shorten Level 3 Notification interval to coincide with Tariff implementation date of February 20, 2007 February 5, 2007

Lynn Stecklein-Qwest stated that the purpose of this meeting is to conduct the vote on an exception request submitted by Qwest. A pre-meeting was held on January 26, 2007 to determine what the yes and no vote would indicate and to answer any questions about this request. She said that Qwest is seeking an exception request to implement a Level 3 notification in a shorter than normal timeframe. The minimum required interval is 31 days. Qwest is requesting the proposed change be implemented in a 29 day interval to match the tariff implementation date of February 20, 2007.

Jeff Farra-Qwest stated that the proposed documentation changes to Tech Pub 77386 include language associated with adding new features to the MOE product related to Collocation. The change is to add Ethernet connectivity options to the optical ITP.

Lynn Stecklein-Qwest reviewed the following:

A vote of ‘Yes’ will indicate a preference to allow PC012307-1EX to be implemented in a 29 day interval to match the tariff implementation date of February 20th.

A vote of ‘No’ will indicate a preference not to allow this request to be implemented in a 29 day interval to match the tariff implementation date of February 20th.

Lynn Stecklein-Qwest stated that a quorum of 5 will be required for the vote to occur on the 5th and requires a 2/3rd’s majority vote in order for this exception to be granted. She stated that 2 yes votes were submitted via e-mail from Sprint and Qwest.

Lynn Oliver-Covad voted yes.

- January 26, 2007

Exception Request Pre-Meeting

Bonnie Johnson-Eschelon voted yes.

Kelly Leverich-Integra voted yes.

Lynn Stecklein-Qwest stated that this request has been granted with 5 yes votes and this CR will be closed.

There were no other questions.