Wholesale: Products & Services

Archived System CR 5372690 Detail

 
Title: TOS Code Removal for Req Type A Loop Ordering
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

5372690 Denied
4/18/2001
-   2/ Unbundled Loop
Originator: Wallace-Jones, Regina
Originator Company Name: Covad
Owner: Routh, Mark
Director:
CR PM: Routh, Mark
Description Of Change
Covad would like the TOS Code removed as an ordering requirement. Although TOS is beneficial to Qwest (helps define billing and customer service), it really has no meaning for the CLEC. In order to accurately specify TOS, we must have access to the CSR, which means additional time and development. Covad would like Qwest to re-evaluate the need for TOS information and consider removing it as an ordering requirement. Information from Manuel Lozano ---- For the TOS field in LSOG 5. Qwest is not adhering to OBF guidelines. The field in LSOG 5 is Conditional for Activities N,C,T,V,W. Condition: Required when the ACT field is "N", "C", "T", "V" or "W" and the first position: of the REQTYP field is "E", "F" or "M" and the LTOS on the service specific form is not populated, otherwise optional. Basically, it is only required for Resale and UNE P/Port Services.

Status History

Date Action Description
Release Information IMA Release 
2/2/2001 Status Changed Status changed to New - To Be Reviewed. 
2/2/2001 Info Sent to CLEC Sent email to Regina Wallace-Jones and Mike Goebel with updated CR 
2/2/2001 CR Submitted Received and status set to New - To be validated. 
2/7/2001 LOE Issued T-Shirt size Large and options provided. Eligible for industry prioritization. 
2/7/2001 Status Changed Reviewed - Under Consideration 
2/8/2001 Info Sent to CLEC Sent email to Regina Wallace-Jones and Mike Goebel with updated CR 
4/2/2001 Record Update Description of changes was updated to include the information that Manuel Lozano provided. 
4/2/2001 Info Sent to CLEC Sent email to Regina Wallace-Jones and Mike Goebel with updated CR. 
4/18/2001 Status Changed CR was denied at the systems cmp meeting 

Project Meetings

CenturyLink Response

The TOS code is a required field per OBF Guidelines. To remove it would cause the loss of order integrity during the CSR processing.

Information Current as of 1/11/2021