Title: Rate Change Notification | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
5043204 |
Withdrawn 12/20/2000 |
- | 12/ |
Originator: Markert, William |
Originator Company Name: Eschelon |
Owner: Thompson, Jeff |
Director: |
CR PM: Routh, Mark |
Description Of Change |
Eschelon seldom receives notification of billing changes (rates/terms/etc.). Qwest simply makes the changes with no explanation of why the changes were made. Proper noficiation should include the rate change or rate structure change with references to specific tariff sections, interconnection sections, or contract sections of applicable documents.
|
Status History |
Date | Action | Description |
8/31/2000 | CR Submitted | New – To be validated |
9/1/2000 | Status Changed | New – To be industry evaluated. Sent email to Kerrie Douglas with CR # and status. |
9/20/2000 | Status Changed | Status changed to Evaluated – To be reviewed. |
9/22/2000 | Status Changed | Status changed to Reviewed – Under consideration. |
9/29/2000 | Additional Information | Sent email to Kerrie Douglas and William D. Markert about status changes. |
10/18/2000 | LOE Issued | T-Shirt Size Small and Option provided in CICMP meeting. Status changed to Hold and will be addressed in the December 20 CICMP meeting when Product and Process is added to CICMP. It is not eligible for industry prioritization. |
11/8/2000 | Info Sent to CLEC | Sent email to William D. Markert with updated CR. |
12/6/2000 | Additional Information | Will address in 12/20 Product/Process CICMP Meeting |
12/20/2000 | Status Changed | CR Cancelled by Lynne Powers |