Archived System CR 4869887 Detail |
Title: Allow IMA GUI users to build LSR templates to use when creating new LSRs. | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
4869887 |
Completed 2/21/2002 |
- | 1/8 | All Products |
Originator: Dowding, Byron |
Originator Company Name: Alltel |
Owner: Routh, Mark |
Director: |
CR PM: Routh, Mark |
Description Of Change |
ALLTEL would like the ability to create templates that can be used when creating new LSRs.
|
Status History |
Date | Action | Description |
Release Information | IMA Release 8.00 | |
6/21/2000 | CR Submitted | Submitted |
6/29/2000 | Status Changed | New - To be industry evaluated. Sent email to Byron Dowding with CR # and status. |
6/29/2000 | Info Sent to CLEC | Sent email to Byron Dowding with CR # and status. |
7/19/2000 | Status Changed | Status changed to Evaluated - To be reviewed. |
7/28/2000 | Info Sent to CLEC | Sent email to Byron Dowding about status change and form change to version 05. |
8/2/2000 | Status Changed | Reviewed - Under consideration |
8/16/2000 | LOE Issued | Received T-shirt size and option during industry team meeting. |
8/29/2000 | Info Sent to CLEC | Sent email to Byron Dowding with updated CR. |
3/21/2001 | Status Changed | CR was put on Hold in the March CICMP meeting. |
3/28/2001 | Info Sent to CLEC | Sent email to Byron Dowding and Dave Hahn with updated CR. |
10/31/2001 | Release Ranking | Ranking for Release 10.0 occurred at October, 2001 CMP Meeting. 4869887 ranked 38 |
1/17/2002 | Status Changed | CR # 4869887 status updated to 'Presented; CR was not packaged as part of 10.0 and is eligible for ranking in 11.0' |
2/8/2002 | Status Changed | The ability to copy an existing LSR to create a new one was put into IMA 8.0 |
2/21/2002 | Status Changed | CR was declared Completed by Byron Dowding and discussed at the Feb. CMP meeting. |
2/21/2002 | Discussed at Monthly CMP Meeting | 4869887 discussed during 'CRs to consider for Closure' portion of February Systems CMP Monthly meeting; please see Attachment E of February Systems CMP Distribution Package |
Project Meetings |
|
CenturyLink Response |
The CLEC will have the ability to copy an existing LSR that can be used to create a new one.
|
Information Current as of 1/11/2021