Archived System CR 4661383 Detail |
Title: Request not to do re certification for EDI upgrade | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
4661383 |
Withdrawn 4/18/2001 |
- | 2/ |
Originator: Osborne-Miller, Donna |
Originator Company Name: AT&T |
Owner: Routh, Mark |
Director: |
CR PM: Routh, Mark |
Description Of Change |
AT&T does not want to do re-certification for EDI upgrades. All testing should be done in testing environment, not with real production data in US West production environment.
|
Status History |
Date | Action | Description |
Release Information | IMA Release | |
4/10/2000 | CR Submitted | Submitted |
4/13/2000 | Status Changed | New - To be industry evaluated |
4/13/2000 | Info Sent to CLEC | Sent email to Adam Li on CR # and status. |
5/17/2000 | Status Changed | Status changed to Evaluated - To be reviewed |
5/26/2000 | Status Changed | Status changed to Reviewed - Under Consideration |
5/26/2000 | Record Update | U S WEST to provide T-shirt size and Option at next industry team meeting on 06/21/00 |
6/11/2000 | Info Sent to CLEC | Sent email to Adam Li on CR status. |
6/21/2000 | LOE Issued | T-shirt size and option provided at industry team meeting. |
7/6/2000 | Info Sent to CLEC | Sent email to Adam Li on CR eligibility for industry prioritization. |
10/18/2000 | Record Update | CR was removed from online CR Prioritization Form since Qwest is in process of resizing this CR. |
11/8/2000 | Info Sent to CLEC | Sent email to Donna Osborne-Miller with updated CR. |
11/15/2000 | LOE Issued | T-Shirt Size Small and Option provided in CICMP meeting. Eligible for industry prioritization. |
12/1/2000 | Info Sent to CLEC | Sent email to Donna Osborne-Miller with updated CR. |
3/21/2001 | Status Changed | CR was placed on Hold during the March CICMP meeting. Qwest provides this ability today. Pending Cancellation |
3/28/2001 | Info Sent to CLEC | Sent email to Donna Osborne-Miller, Lydell Peterson &Tim Bessey with updated CR. |
4/18/2001 | Status Changed | This CR was canceled by AT&T at the April CICMP meeting |
4/26/2001 | Info Sent to CLEC | Sent email to Donna Osborne-Miller, Lydell Peterson &Tim Bessey with updated CR. |
12/18/2001 | Record Update | Changed status from 'Cancelled CLEC' to 'Withdrawn' for database cleanup |
Project Meetings |
|
CenturyLink Response |
|
Information Current as of 1/11/2021