Archived System CR 4441217 Detail |
Title: PIC verification on POTS, Centrex 21, Centrex Plus, and Centron lines as indicated in the USW switch. | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
4441217 |
Completed 11/15/2001 |
- | 3/8 |
Originator: Powers, Lynne |
Originator Company Name: Eschelon |
Owner: Routh, Mark |
Director: |
CR PM: Routh, Mark |
Description Of Change |
ATI requires the ability to verify the PIC for it’s POTS, Centrex 21, Centrex Plus and Centron lines as indicated in the switch vs. IMA.
|
Status History |
Date | Action | Description |
Release Information | IMA Release 8.00 | |
1/19/2000 | CR Submitted | Received CR |
1/20/2000 | Status Changed | Logged CR. Status New - To be industry evaluated. |
1/20/2000 | Info Sent to CLEC | Sent email to Lynn Powers on CR status. |
1/24/2000 | Status Changed | Status Evaluated - To be reviewed. |
2/2/2000 | Info Sent to CLEC | Sent email to Lynn on status change on 01/24/00, update of CR form to version 04, and prioritization process category to GUI. |
2/3/2000 | Status Changed | Status Reviewed - Under Consideration |
2/8/2000 | Info Sent to CLEC | Sent email to Lynn on status change. |
2/16/2000 | LOE Issued | Received T-Shirt Size and Option during industry team meeting. Also removed the X Large Option. |
2/18/2000 | Info Sent to CLEC | Sent email to Lynn on update of CR Form. |
10/18/2000 | Status Changed | Status changed to Reviewed - Release Baseline Candidate. Selected as Co-Provider CR for target IMA Release 8.0. |
10/18/2000 | LOE Issued | |
11/8/2000 | Info Sent to CLEC | Sent email to Lynne Powers with updated CR. |
1/12/2001 | Info Sent to CLEC | Sent email to Lynne Powers and Judy Rixe with updated CR. Release Baseline Candidate IMA 8.0. |
1/12/2001 | Status Changed | Status changed back to Reviewed - Under Consideration. |
9/10/2001 | Record Update | IMA 8.0 Released |
10/18/2001 | Discussed at Monthly CMP Meeting | Discussed at CMP meeting, Eschelon agreed to change status to "CLEC Test" |
10/18/2001 | Status Changed | Eschelon agreed to change status to "CLEC Test" at October CMP Meeting |
11/15/2001 | Status Changed | Eschelon agreed to change status to "Completed" at November CMP Meeting |
11/15/2001 | Discussed at Monthly CMP Meeting | Discussed at Nov CMP meeting, Eschelon agreed to change status to "Completed" |
Project Meetings |
|
CenturyLink Response |
|
Information Current as of 1/11/2021