Archived System CR 4381555 Detail |
Title: Re Certification | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
4381555 |
Withdrawn 2/16/2000 |
- | 2/ |
Originator: Sumner, Steve |
Originator Company Name: Sprint |
Owner: Routh, Mark |
Director: |
CR PM: Routh, Mark |
Description Of Change |
Sprint wants USW to stop requiring CLECs re-certify for testing & production each time a new release goes out. CLECs should only have to get certified once. Having to go through the re-certification process each time a release is sent out (point or major) puts restrictions on CLECs that delay market entry and forces them to incur unneeded expense.
|
Status History |
Date | Action | Description |
Release Information | IMA Release | |
12/22/1999 | CR Submitted | Submitted CR while on holiday |
12/28/1999 | Status Changed | Logged CR and status of "New - To be industry evaluated". |
12/28/1999 | Info Sent to CLEC | Sent email to Steve Sumner on log #, OSS interface, and status with copy to account manager. |
12/28/1999 | Record Update | Also, selected OSS interface as IMA EDI. |
1/24/2000 | Status Changed | Status Evaluated - To be reviewed |
2/2/2000 | Info Sent to CLEC | Sent email to Steve on status and update CR form to version 04. |
2/3/2000 | Status Changed | Status change to Reviewed - Under Consideration |
2/8/2000 | Status Changed | Sent email to Steve on status change. |
2/8/2000 | Info Sent to CLEC | Sent email to Steve on status change. |
2/16/2000 | Status Changed | Cancelled - Co-Provider |
2/18/2000 | Info Sent to CLEC | Sent email to Steve on CR status. |
12/18/2001 | Record Update | Changed status from 'Cancelled CLEC' to 'Withdrawn' for database cleanup |
Project Meetings |
|
CenturyLink Response |
|
Information Current as of 1/11/2021