Archived System CR 4121257 Detail

 
Title: US West IMA Internet Access
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

4121257 Completed
5/16/2001
-   1/7
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Thompson, Jeff
Director:
CR PM: Routh, Mark
Description Of Change
This is to check if US West has plans to make IMA accessible via Public Internet (ie: GTE WISE and Bell Atlantic DCAS for CLEC) rather than Dial-Up. Dial-Up prevents NT users from accessing their network Printers, when connected to US West.

Status History

Date Action Description
Release Information IMA Release 7.00 
9/15/1999 CR Submitted  
9/20/1999 CR Acknowledged Provide initial status of New To be industry reviewed. Sent email to contact person on log # and status 
9/21/1999 Status Changed Update Status to Evaluated – To be reviewed. Sent email to contact person and Jeff Bisgard on status change and adding additional fields (i.e., Co-Provider Priority Level and # per team meeting.) 
9/22/1999 Discussed at Monthly CMP Meeting Jim Bisgard with AT&T presented this CR at the Co-Provider Industry Team Meeting. 
9/29/1999 Status Changed Update Status to Reviewed Under Consideration. Sent email to contact person, Jeff Bisgard, and copy to Account Manager on status change. Informed them that it is currently on a list of CRs to be considered for a release candidate for Release 5.1. 
10/18/1999 Status Changed Noticed status change to Evaluate – To be reviewed occurred on 09/23/99 not 09/21/99 as recorded above. Correction is seen on Co-Provider CR Log. Sent email to Martinez and Bisgard on this error/correction. 
11/2/1999 Additional Information Updated form to Version 03 and added in CICMP Manager Section Prioritization Process Category types and selected GUI per Co-Provider Industry Issue/Action #34. Sent email to contact person and Jeff Bisgard informing them of the addition and att CR. 
11/18/1999 Record Update Industry team CR review and prioritization. 
1/24/2000 LOE Issued U S WEST provided T-shirt size and options 
2/1/2000 Record Update Sent email to Jeff Bisgard and Surawud Martinez on updating the CR form to Version 04. Also, pointed out that the CR is not being considered for Release 6.0 (previously 5.1) as stated on 09/29/99. 
3/6/2000 Record Update Updated CR to reflect Adam Li as submitter. Sent email to Adam 
4/19/2000 Record Update Reviewed – Release Baseline Candidate for IMA Release 7.0 based on T-shirt size X-Large and Option Description. . Voted/Selected as Co-Provider CR Option for 7.0. 
5/1/2000 Baseline Candidate Selection Sent email to Adam on CR status/candidate 
11/13/2000 Record Update Updated prioritization level and # and sent email to Jeff Bisgard. 
5/16/2001 Status Changed Status changed to Completed - In production 
3/19/2002 Record Update Sent email to Donna Osborne-Miller, Tim Bessey and Lydell Peterson with updated CR. 

Project Meetings

CenturyLink Response

Information Current as of 1/11/2021