Title: Flow Through SUP 1 Handling
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

30214 Completed
3/21/2002
-   3/9 All
Originator: Gallegos, John
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Routh, Mark
Description Of Change
All SUP 1 LSRs currently flow through. New connects cannot be cancelled automatically because the AN is not available. As a result, all SUP 1 LSRs with ACT=N error.

Status History

Date Action Description
Release Information IMA Release 9.00 
10/23/2001 CR Submitted CR transferred from legacy database to CMP database 
10/24/2001 Baseline Candidate Selection CLECs notified this CR was a selected CR Baseline Candidate. 
1/17/2002 Discussed at Monthly CMP Meeting CR # 30214 discussed during 9.0 Candidate discussion (Attachment H in January Distribution Package)' 
2/25/2002 Status Changed 30214 status updated to 'CLEC Test' based upon 2/25/02 implementation of IMA 9.0 
3/21/2002 Status Changed Reviewed in the 3/21/02 CMP meeting and Closed. 
3/21/2002 Discussed at Monthly CMP Meeting 30214 discussed March Systems CMP Monthly meeting; please see Systems CMP Distribution Package March CMP - Attachment E 