Wholesale: Products & Services

Archived System CR 27751 Detail

 
Title: Intrabuilding Cable.
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

27751 Withdrawn
2/21/2002
3000 - 5500   3/ Intrabuilding Cable
Originator: Sumner, Steve
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Routh, Mark
Description Of Change
An Intra-Building Cable (IBC) is a 2 wire or 4 wire facility that extends from a building terminal or other accessible terminal that services one Multi-Tenant Environment (MTE) building on a property to the end-user’s network interface device (NID).

A CLEC obtains access to the IBC at an established MTE-POI arrangement. The MTE-POI product allows the CLEC to cross-connect at the building terminal for Multi-Tenant Environment Buildings.

The following forms will be used between Qwest and the Co-Provider for ordering IBC:

* LSR - Local Service Request

* EU - End User Information

* LS – Loop Service Request

Status History

Date Action Description
9/28/2001 CR Submitted CR transferred from legacy database to CMP database 
10/18/2001 Discussed at Monthly CMP Meeting Presented at Oct CMP meeting 
10/25/2001 Status Changed Prioritization list sent to all CLECs for IMA 10.0 ranking, status changed to prioritization 
10/31/2001 Release Ranking Ranking for Release 10.0 occurred at October, 2001 CMP Meeting. 27751 ranked 33 
1/17/2002 Status Changed CR # 27751 status updated to 'Presented; CR was not packaged as part of 10.0 and is eligible for ranking in 11.0' 
2/13/2002 Record Update LOE updated from Medium to Large 
2/14/2002 Status Changed Status updated from Presented to Pending Withdrawal; submitter no longer wishes to pursue CR 
2/21/2002 Discussed at Monthly CMP Meeting 27751 discussed during 'CRs to consider for Closure' portion of February Systems CMP Monthly meeting; please see Attachment E of February Systems CMP Distribution Package; AT&T indicated that they might want to sponsor this CR 
3/8/2002 Status Changed This CR was presented for withdrawal by Qwest at the Feb 2002 Systems CMP meeting. Subsequently, AT&T asked to delay the withdrawal until they checked to see if they wanted to sponsor it. AT&T has decided not to sponsor this CR. 

Project Meetings

CenturyLink Response

Information Current as of 1/11/2021