Archived System CR 25505 Detail |
Title: Line Splitting for UNE P accounts | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
25505 |
Withdrawn 3/19/2002 |
3000 - 5500 | 3/ | UNE-P |
Originator: Sumner, Steve |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Routh, Mark |
Description Of Change |
Accept LSR for line sharing on a UNE-P account, class of service UHR. Accept LSR issued by the provider of UNE-P that contains splitting information regarding the DLEC. Accept the LSR with information for central office based and remote line sharing. Enhance loss and completion report for Line Splitting goes to CLEC (owner of UNE-P). Allow line sharing USOCs to appear on the UNE-P (class of service UHR) account to provision and bill. NC/NCI codes for Line Splitting are requested and will be provided at a later date. Conditioning is allowed on Line Splitting, the TRAK fid will be used. Basic installation is the only installation option available for Line splitting
|
Status History |
Date | Action | Description |
9/28/2001 | CR Submitted | CR transferred from legacy database to CMP database |
10/18/2001 | Discussed at Monthly CMP Meeting | Presented at Oct CMP meeting |
10/25/2001 | Status Changed | Prioritization list sent to all CLECs for IMA 10.0 ranking, status changed to prioritization |
10/31/2001 | Release Ranking | Ranking for Release 10.0 occurred at October, 2001 CMP Meeting. 25505 ranked 47 |
1/17/2002 | Status Changed | CR # 25505 status updated to 'Presented; CR was not packaged as part of 10.0 and is eligible for ranking in 11.0' |
1/31/2002 | Status Changed | Status updated to "Pending Withdrawal" from "Presented"; submitter sought to cancel the UR in November; status updated in order to take CR to February CMP meeting |
2/13/2002 | Record Update | LOE updated from Medium from Large |
2/21/2002 | Discussed at Monthly CMP Meeting | 25505 discussed during 'CRs to consider for Closure' portion of February Systems CMP Monthly meeting; please see Attachment E of February Systems CMP Distribution Package; AT&T indicated that they might want to sponsor this CR |
3/19/2002 | Status Changed | AT&T has decided not to sponsor this CR. As a result, it is closed. |
Project Meetings |
|
CenturyLink Response |
|
Information Current as of 1/11/2021